Inventory Reorder Point: worked example
| Annual unit demand | 12,000 |
|---|---|
| Supplier lead time | 14.0 days |
| Safety stock | 500 |
| Reorder point | 960.3 |
| Average daily demand | 32.9 |
| Lead-time demand before safety stock | 460.3 |
Inventory Reorder Point: formula
Common error: Assuming that half of observations must exceed their arithmetic mean. That statement describes neither skewed demand nor irregular lead times. Safety stock needs a chosen service objective and measured variability, not that assumption.
Annual unit demand divided by 365 gives average daily demand. Supplier lead time is the number of days between placing an order and having it on the shelf, using the realistic figure rather than the quoted one, since delays are common. Safety stock is the extra inventory kept for demand or lead-time surprises; it can come from the safety stock calculator or from experience.
Use consistent units for demand and lead time.
Inventory Reorder Point: changing Annual unit demand
| Annual unit demand | Reorder point | Average daily demand | Lead-time demand before safety stock |
|---|---|---|---|
| 9,600 | 868.2 | 26.3 | 368.2 |
| 10,800 | 914.2 | 29.6 | 414.2 |
| 12,000 (example) | 960.3 | 32.9 | 460.3 |
| 13,200 | 1,006.3 | 36.2 | 506.3 |
| 14,400 | 1,052.3 | 39.5 | 552.3 |
Inventory Reorder Point: compare input ranges
| Input | Tested from | To | Reorder point: low input | Reorder point: high input | Swing |
|---|---|---|---|---|---|
| Safety stock | 450 | 550 | 910.3 | 1,010.3 | 100 (10%) |
| Annual unit demand | 10,800 | 13,200 | 914.2 | 1,006.3 | 92.1 (9.6%) |
| Supplier lead time | 13.0 days | 15.0 days | 927.4 | 993.2 | 65.8 (6.8%) |
Inventory Reorder Point: individual input comparisons
| Input | Value | Reorder point | Average daily demand | Lead-time demand before safety stock |
|---|---|---|---|---|
| Annual unit demand | 9,600 | 868.2 | 26.3 | 368.2 |
| 10,800 | 914.2 | 29.6 | 414.2 | |
| 12,000 | 960.3 | 32.9 | 460.3 | |
| 13,200 | 1,006.3 | 36.2 | 506.3 | |
| 14,400 | 1,052.3 | 39.5 | 552.3 | |
| Supplier lead time | 11.0 days | 861.6 | 32.9 | 361.6 |
| 13.0 days | 927.4 | 32.9 | 427.4 | |
| 14.0 days | 960.3 | 32.9 | 460.3 | |
| 15.0 days | 993.2 | 32.9 | 493.2 | |
| 17.0 days | 1,058.9 | 32.9 | 558.9 | |
| Safety stock | 400 | 860.3 | 32.9 | 460.3 |
| 450 | 910.3 | 32.9 | 460.3 | |
| 500 | 960.3 | 32.9 | 460.3 | |
| 550 | 1,010.3 | 32.9 | 460.3 | |
| 600 | 1,060.3 | 32.9 | 460.3 |
Inventory Reorder Point: combined input changes
| Annual unit demand / Supplier lead time | 11.0 days | 14.0 days | 17.0 days |
|---|---|---|---|
| 9,600 | 789.3 | 868.2 | 947.1 |
| 10,800 | 825.5 | 914.2 | 1,003 |
| 12,000 | 861.6 | 960.3 | 1,058.9 |
| 13,200 | 897.8 | 1,006.3 | 1,114.8 |
| 14,400 | 934 | 1,052.3 | 1,170.7 |
Inventory Reorder Point: which assumptions move the result?
Inventory Reorder Point: values and definitions
| Quantity and definition | Value used |
|---|---|
| Annual unit demand | 12,000 |
| Supplier lead time | 14.0 days |
| Safety stock | 500 |
| Reorder point | 960.3 |
| Average daily demand | 32.9 |
| Lead-time demand before safety stock | 460.3 |
Inventory Reorder Point: half and double Safety stock
| Safety stock | Reorder point |
|---|---|
| 250 | 710.3 |
| 500 | 960.3 |
| 1,000 | 1,460.3 |
The calculation assumes steady demand, so seasonal or promotional spikes need a higher point at those times. Supplier reliability changes lead time, and a longer delay raises the required stock. It does not decide the order quantity, which is the economic order quantity's role.
Items with lumpy demand need a different approach.
Business Finance calculators: Inventory Carrying Cost Calculator, Target Price and Margin Calculator, Pallet / Box Loading Calculator, Straight-Line Depreciation Calculator, Double Declining Balance Depreciation Calculator, GDP Calculator.
A reorder point set from average demand alone runs out during any month that's busier than average, because the point is supposed to cover demand during the lead time it takes a new order to arrive. Average demand times average lead time leaves no room at all for a demand spike or a delayed shipment during that exposed window.
Confirm the safety-stock component reflects your actual demand variability and supplier reliability, not just a padded guess, since that's the piece doing the real protective work.
Set the order size with the economic order quantity calculator, and derive the safety stock from a service level with the safety stock calculator. The inventory turnover and carrying cost pages show the cost of holding more. Review slow-moving items separately.
What is a reorder point?
The inventory level that triggers a new order, equal to the demand expected during the supplier's lead time plus safety stock.
What happens if lead time doubles?
Lead-time demand doubles, so the reorder point rises sharply. Track supplier performance and update the figure when delivery times change.
Why include safety stock?
It protects against demand higher than average or deliveries later than promised, which would otherwise cause stockouts.