Takt Time Calculator

Takt time is the pace of production needed to meet demand: one unit every so many minutes. 450 minutes for 90 units is one unit every 5 minutes, or 300 seconds. Compare it with your cycle time: if a station takes longer than takt time, it is the bottleneck and the line falls behind.

Takt time is used to balance work among stations and decide how many people and machines are needed.

Takt Time Calculator: inputs

Calculated result
Takt time (minutes per unit)5
Takt time (seconds per unit)300

Takt Time Calculator: Available production time (minutes) sensitivity

Takt Time Calculator: Available production time (minutes) and Takt time (minutes per unit)5 calculations vary the “Available production time (minutes)” input while holding the other entered inputs constant.36044054.545054955.55406

Takt Time: worked example

Available production time (minutes)450
Customer demand (units)90
Takt time (minutes per unit)5
Takt time (seconds per unit)300

Takt Time: formula

Takt time = available production time ÷ customer demand

Lean Enterprise Institute: takt time

Common error: Confusing takt time with cycle time. Takt time is set by demand, while cycle time is how long a station really takes, and the two are compared to find the gaps.

Available production time is the time per shift or day in which the line can run, after breaks, meetings and planned maintenance, in minutes. Customer demand is the number of units the customer requires in that period, taken from orders or a demand forecast. Use consistent units.

If demand varies by day or season, calculate takt time for the peak as well as for the average.

Takt Time: changing Available production time (minutes)

Available production time (minutes)Takt time (minutes per unit)Takt time (seconds per unit)
3604240
4054.5270
450 (example)5300
4955.5330
5406360

Takt Time: compare input ranges

InputTested fromToTakt time (minutes per unit): low inputTakt time (minutes per unit): high inputSwing
Available production time (minutes)4054954.55.51 (20%)
Customer demand (units)81995.64.51 (20%)

Takt Time: individual input comparisons

InputValueTakt time (minutes per unit)Takt time (seconds per unit)
Available production time (minutes)3604240
4054.5270
4505300
4955.5330
5406360
Customer demand (units)726.3375
815.6333.3
905300
994.5272.7
1084.2250

Takt Time: combined input changes

Available production time (minutes) / Customer demand (units)7290108
360543.3
4055.64.53.8
4506.354.2
4956.95.54.6
5407.565

Takt Time: which assumptions move the result?

Takt Time: Takt time (minutes per unit) as Available production time (minutes) changesTakt time (minutes per unit) starts at 4. Moving Available production time (minutes) from 360 to 540 changes it to 6, with Customer demand (units) 90 kept fixed.36044054.545054955.55406
Chart quantityDisplayed settings
Available production time (minutes)360 → 540
Takt time (minutes per unit)4 → 6
Customer demand (units)90
Takt Time: Takt time (minutes per unit) as Customer demand (units) changesTakt time (minutes per unit) starts at 6.3. Moving Customer demand (units) from 72 to 108 changes it to 4.2, with Available production time (minutes) 450 kept fixed.726.3815.6905994.51084.2
Chart quantityDisplayed settings
Customer demand (units)72 → 108
Takt time (minutes per unit)6.3 → 4.2
Available production time (minutes)450

Takt Time: values and definitions

Quantity and definitionValue used
Available production time (minutes) — Shift length less breaks and planned stops.450
Customer demand (units) — Units needed in that same time.90
Takt time (minutes per unit)5
Takt time (seconds per unit)300

Takt Time: half and double Available production time (minutes)

Available production time (minutes)Takt time (minutes per unit)
2252.5
4505
90010

Takt time is driven by demand, not by machine capacity, and it is a target, not a measurement of actual speed. It does not account for downtime, defects or changeovers unless you adjust available time. Frequent changes in demand require recalculating.

Mixed-model lines need a weighted figure.

Business Finance calculators: Safety Stock Calculator, Little's Law Calculator, Conversion Rate Calculator, A/B Test Significance Calculator, Overhead Rate Calculator, Gross Profit and Margin Calculator.

Takt time is the pace a production line must hold to meet demand: available time divided by the units the customer needs. A shift with 450 minutes of production and demand for 90 units has a takt time of 5 minutes per unit, or 300 seconds. If a station takes longer than that, it becomes the bottleneck, and a station that is far faster is idle or overproducing.

Use time available for production. Breaks, meetings and planned maintenance come out before you divide.

Compare with the overall equipment effectiveness calculator to see whether the line can hit the pace, and Little's law for the inventory needed in the flow. The safety stock and reorder point pages address materials. Balance the work so each station's cycle time is just under takt.

What is the difference between takt time and cycle time?

Takt time is how often you must produce a unit to meet demand, and cycle time is how long a station takes to produce one. Cycle time must not exceed takt time.

How do I calculate available time?

Subtract breaks, meetings and planned stops from the shift length. Only the time the line can produce counts.

What happens if demand changes?

Takt time changes in inverse proportion, so a 20% rise in demand cuts takt time by about 17%, and you must adjust staffing and stations.